U-shaped baffles with horizontal-tooth carriers
Reading the Drawing
The horizontal-tooth carrier locates the folded U-shaped baffles. Strip hangers connect this carrier to the main framework.
Numbered Component Key
Match each number to the label below. Dimensions shown on the drawing are in millimeters unless noted.
- M8 galvanized hanger rod
- 38/50 main-carrier hanger
- Horizontal-tooth carrier
- Strip-carrier hanger
- 38/50 main carrier
- U-shaped baffle
- Folded U-shaped baffle
- Galvanized hanger rod
- Height
- Base width
- Baffle height
Installation Steps
- Measure the finished ceiling elevation from the design drawings. Mark the level line and fix the perimeter angle along the walls.
- Establish the installation direction. Drill suspension points in the structural ceiling at no more than 1,200 mm spacing and secure the galvanized hanger rods with expansion anchors.
- Fit the main-carrier hangers and light-steel main carriers. Adjust their height and level, keeping the carriers parallel.
- Use strip hangers to connect the horizontal-tooth carriers to the main carriers. Level the secondary carriers; keep them parallel to one another and perpendicular to the main carriers.
- Fit the U-shaped baffles into the matching secondary-carrier clips, working in one direction.
- Measure perimeter panels on site, cut them to fit and support their edges on the perimeter angle.
- Keep hands clean during installation. Avoid sweat, oil and other contamination on the finished surface.