Low-edge panels with triangular carriers
Reading the Drawing
The panel returns clip into triangular carriers. The component views show the triangular carrier, splice connector and hanger.
Numbered Component Key
Match each number to the label below. Dimensions shown on the drawing are in millimeters unless noted.
- Triangular carrier
- Carrier connector
- Triangular-carrier hanger
- M8 galvanized hanger rod
- 38/50 main carrier
- Ceiling panel
- Low-edge ceiling panel
Installation Steps
Components: M8 galvanized rods; 38/50 light-steel main carriers; triangular-carrier hangers and connectors; low-edge panels.
- Measure the finished ceiling elevation from the design drawings. Mark the level line and fix the perimeter angle along the walls.
- Establish the installation direction. Drill suspension points in the structural ceiling at no more than 1,200 mm spacing and secure the galvanized hanger rods with expansion anchors.
- Fit the main-carrier hangers and light-steel main carriers. Adjust their height and level, keeping the carriers parallel.
- Use triangular-carrier hangers to connect the triangular concealed carriers to the main carriers. Level the secondary carriers; keep them parallel to one another and perpendicular to the main carriers.
- Align the two clip edges with the triangular-carrier slots. Gently press upward along the panel edges until the folded edges lock into the carrier.
- Measure perimeter panels on site, cut them to fit and support their edges on the perimeter angle.
- Keep hands clean during installation. Avoid sweat, oil and other contamination on the finished surface.