Buy a finish as a defined coating system, not as the word “PVDF” or “powder”. Start from the exposure, the panel shape and the performance required, then agree application route, pretreatment, film build, cure and inspection. This guide compares the three production routes and shows how to read a coating inspection so thin areas and uncoated returns are caught.
What should the tender say about PVDF versus powder coating?
PVDF names a resin; powder names an application form. Compare the named products, the pretreatment and the tested performance for the project exposure, then state how the formed panel is coated. In practice, PVDF is the standard choice for exterior and coastal facades, and polyester powder for interior ceilings and walls.
| Purchase decision | Liquid PVDF system | Architectural powder system |
|---|---|---|
| Product identity | Name the coating supplier, resin specification, primer and topcoat system. | Name the powder supplier, product code, chemistry and durability class. |
| Project exposure | Identify exterior weathering, coastal exposure, color and gloss retention requirements. | Confirm the selected product is intended for the actual interior or exterior exposure; not all powders have the same durability. |
| Film build and cure | State the specified layers, dry-film thickness and curing conditions for the named system. | State the required film thickness and cure schedule; include recesses and folded returns in inspection. |
| Evidence for approval | Request the system data sheet, approved sample and relevant test evidence. | Request the system data sheet, approved sample and relevant test evidence. |
| Comparable price | Quote the same substrate, pretreatment, panel geometry, color, finish area and quantity. | Use the same comparison schedule; do not compare a generic powder price with a fully specified exterior system. |
Where a tender names a performance standard, ask for evidence for the complete coating system and the edition required. Warranty terms are stated in the order documents; test reports can be provided with your quotation.
Apply the finish schedule to exterior solid aluminum cladding panels, and use the finish sample approval guide before releasing production.
How do the three coating production methods compare?
| Method | What happens | Where it fits | What to specify |
|---|---|---|---|
| Liquid spray coating | Liquid paint is sprayed onto the prepared surface, then cured to its system requirements | Fabricated panels with returns, curves and formed details | Resin/product, primer and topcoat system, coverage, dry-film thickness and curing requirements |
| Roll / coil coating | Coating is metered onto flat moving strip; the coated material is subsequently fabricated | Sheet products designed for forming from prefinished material | Front/back coatings, formability, bend requirements and exposed cut-edge treatment |
| Powder coating | Electrostatically charged powder is deposited on the prepared part and heat-cured | Conductive metal parts suitable for the selected application and curing process | Powder chemistry, film thickness, recess coverage, texture, cure schedule and exposure rating |
Post-coated panels are finished after fabrication; prefinished sheet carries its coating through cutting and forming. The route decides where surface damage and bend performance are controlled, so choose it with the panel geometry. Lianhui post-coats formed panels on its own lines.
Which coating chemistry suits the exposure?
Polyester and fluoropolymer systems come in different formulations and performance classes, and exterior-grade powders exist alongside interior ones. Name the actual coating system and the performance required.
For interior ceilings, color, texture, cleaning and surface tests usually decide. For exposed facades, add weathering, corrosion and color-retention evidence for the location, and mention coastal or industrial exposure in the enquiry.
If the project specifies AAMA 2603, 2604 or 2605, give the document and edition. They are performance specifications for organic coatings on architectural aluminum; ask for test evidence for the proposed system.
Are pretreatment and curing part of the finish?
Pretreatment removes contamination and prepares the surface for the chosen coating: cleaning, rinsing, compatible chemical pretreatment and drying. Changing the paint means checking that the pretreatment still suits it.
Preparation, application and cure records stay linked to the panel batch and coating system.
Cure follows the coating maker’s conditions for the workpiece; the record shows how production confirms the time and temperature each panel actually reached.
How do you read coating thickness with the correct units and system?
1 micrometre (µm) = 0.001 mm. A 60 µm coating is 0.060 mm, not a 0.6 mm sheet. Record substrate and coating thickness in separate fields, and state whether a value is the topcoat or the total dry film of a multi-layer system.
The right film thickness is the one in the coating specification for that application method. Coil and post-applied systems use different builds, so compare required performance, not the larger number.
| Check | What it evaluates | What the order should identify |
|---|---|---|
| Dry-film thickness | Applied film build at the measured locations | Layer or total film, target/range, method and measurement locations |
| Adhesion | Attachment of the coating under the specified test | Method, conditioning and acceptance criterion |
| Colour and gloss | Agreement with the approved appearance | Retained sample, colour-difference method where used, gloss geometry and limits |
| Bending / impact | Behaviour under the specified deformation or impact | Test method and applicable panel/coating construction |
| Exposure testing | Behaviour under stated weathering or corrosion conditions | Test type, duration, acceptance limits and the system represented |
Can a passing average thickness hide a thin area?
Inspection plan: the purchase specification requires 60–100 µm at each defined inspection location on the exposed face. Five location results are 72, 76, 81, 78 and 48 µm.
The arithmetic mean is 71 µm, inside the range. The 48 µm location is nevertheless below the specified minimum. Under this location-by-location rule, the panel is held for investigation; it is not accepted on the average alone.
The 60–100 µm band is a typical powder requirement. Before measuring, write down whether limits apply to single readings or location averages, follow the test method for the number of readings, and record the actual values.
| Record | Entry |
|---|---|
| Finish identity | Finish F-07 / production batch B-03 / exposed face |
| Measurement map | Locations A–E marked on the panel sketch; returns recorded separately |
| Results | A 72; B 76; C 81; D 78; E 48 µm |
| Decision | Hold P-014. Confirm the measurement and map the extent of the thin area. |
| Close-out | Record the approved disposition and repeat the required checks after rework. |
Use a gauge for non-conductive coatings on aluminum, calibrated on the same substrate. Thin sheet, curves and edges affect readings, so follow the instrument instructions. Thickness, appearance and adhesion are recorded as separate results.
How do you tell a finish defect from a substrate defect?
| Observation | What to investigate | What to avoid |
|---|---|---|
| Raised specks along a worked joint | Examine the uncoated surface preparation and removal of weld spatter. | Assuming another coat will hide a protruding substrate defect. |
| Uneven orange-peel texture on a smooth finish | Compare with the agreed texture sample under the same viewing conditions; review application and curing records. | Rejecting a deliberately textured finish against a smooth-finish sample. |
| Thin or missed finish in a recess | Check the coverage requirement, part orientation and accessible measurement areas. | Using a centre-face result to represent every return and recess. |
Identify the panel and area before repair, and choose between local touch-up and full recoating according to the defect and the specified system.
What should geometry and coverage confirm before sample approval?
Flat color chips start the discussion; formed panels add returns, corners, recesses and visible edges. Approve coverage and appearance on a representative fabricated sample, delivered in 3–5 working days. For prefinished sheet, inspect after bending and agree how cut edges are treated.
Inspect runs, bubbles, contamination, thin or missed areas and handling damage separately from color. If a check fails, isolate the batch and find the cause before choosing repair or recoating.
What should you check in the coating submission before comparing warranties?
Ask for the coating product designation, the applicator and the list of specified tests. A paint approval, a coater licence and a test on a finished specimen each answer a different question. Where a quality label is required, check its current scope covers the plant and system proposed.
For each report, record substrate, pretreatment, layers, test method and property, and compare them with the production proposal. Read the warranty’s exclusions, repair procedure and maintenance obligations before ordering.
How do you handle hidden returns, recesses and cut edges?
Mark each surface on the drawing: exposed face, visible return, shadow joint, back face, concealed fixing zone. State which get the decorative finish and which get another treatment, so “fully coated” means the same thing to everyone.
Deep recesses are harder to powder-coat evenly, and prefinished sheet needs checking at formed corners and cut edges. Include one difficult detail in the first production approval.
What should accompany the delivered finish?
- A finish code linked to the approved sample and panel schedule.
- Batch identification and inspection results, including any rework.
- Cleaning instructions and limits on site chemicals and protective-film removal.
- A procedure for reporting damage, approving repairs and ordering matching replacements.
Photograph unopened packaging and affected panel IDs before unpacking further, and test any touch-up on a spare before using it on the elevation.
What does a complete finish enquiry include?
- Interior/exterior location and exposure conditions.
- Panel alloy (AA1100 standard, AA3003 on request), geometry and surfaces to be coated.
- PVDF, polyester powder or wood-grain, and any performance standard.
- Color, gloss, texture and retained-sample reference.
- Inspection methods, acceptance limits and batch records required.
- Warranty scope, cleaning requirements and packing protection.